RÍO CLARO CEMENT PLANT

Antioquia, Colombia

Project Details

Location

Antioquia, Colombia

Industry

Cement

Download Case Study

Alimak SL-H 2000 Installation at Río Claro Cement Plant, Colombia

In 2024, Alimak, in collaboration with our long-standing Colombian distributor Hekcacol, delivered an Alimak SL-H 2000 elevator to the Río Claro cement plant in Sonsón, Antioquia, Colombia.

The SL-H 2000 elevator was installed in the plant’s clay premix tower, providing critical vertical access for mobilising personnel, materials, and tools. Cementos Argos, the operator of the Río Claro plant, has been increasingly focused on sustainability, including the production of calcined clay cement, a more environmentally friendly alternative. The Alimak SL-H 2000 is key in ensuring operational efficiency and helping the plant meet its production and maintenance goals.

The main challenge was positioning the elevator in the optimal location on the tower without incurring significant additional costs. Existing structural elements had to be carefully relocated to allow for the elevator’s installation while minimising disruptions to the plant’s operations.

As Cementos Argos shifts towards greener cement production, including using calcined clay to reduce carbon emissions, Alimak’s elevator helps improve operational efficiency. Alimak remains committed to helping our clients improve their sustainability impact by providing durable, long-lasting solutions.

Cementos Argos chose Alimak because of our strong reputation and technical support, including installation, maintenance, and spare parts provided by Hekcacol in Colombia. This ensures a reliable, long-term solution for vertical access in their operations.

The Alimak SL-H 2000 elevator was installed, covering 7 landings with a lifting height of 40.5 metres. Its 2,000 kg capacity allows for safely transporting people and materials, ensuring smooth, efficient operations in the plant’s clay premix tower. The elevator’s robust design and performance are crucial for keeping up with Cementos Argos’ maintenance needs as they continue to focus on greener production practices.

ELEVATOR DETAILS
Location: Río Claro Cement Plant, Antioquia, Colombia
Industry: Cement
Application: Clay Premix Tower
Elevator type: Rack and Pinion
Elevator model: Alimak SL-H 2000
Capacity: 2,000 kg
Speed: 0.9 m/s
Lifting height: 40.5 m

Get in touch for more information or a quote

Need help selecting the right product for an upcoming project? Get in touch with our product experts for information on the range of vertical access solutions available and a quotation to meet the needs of your project.

Request a Quote

Find a local representative

Present across six continents, Alimak utilises a global network to deliver vertical access solutions for a wide range of applications on construction and industrial sites around the world. Get in touch to find a local representative from Alimak’s global network.

Search Directory