Ten Alimak mast climbing work platforms are being used during the construction of a new building block in Berlin, Germany.
The German Trade Union Confederation, Deutscher Gewerkschaftsbund (DGB) is building a new office and commercial building in the Berlin Schöneberg district.
The new office building of approximately 21,000 m² will be used by the federal board administration of the DGB. The new building elements with different heights blend together to create a distinct structure with a unified appearance.
Alimak was approached to supply an efficient vertical access solution for mounting the new façade elements and windows of the DGB building.
Anchoring of the mast towers created a challenge with reconstruction from standard anchoring to special consoles required. Alimak provided a forcible technical solution for the mounting of windows and facade with a total of ten mast climbing work platforms, from its German rental fleet. The project commenced in September 2021 and is ongoing until today.
PLATFORM DETAILS
Project: DGB – Schöneberg Office Tower
Location: Schöneberg, Berlin, Germany
Application: High-rise construction
Product category: Mast climbing work platforms
Models: Alimak MC 450 and MSHF
No. of platforms: 10
Platform sizes: 1.2–2.2 x 8.4–28.5 m (W x L)
Capacity: Up to 2,000 kg
Speed: 7–9 m/min
Lifting height: Varies between 22–49 m